CONSTRUCTION

 

•  All projects that are greater than 1 acre in soil disturbance must comply with     the State General Construction Permit and prepare a Storm Water Pollution     Prevention Plan(SWPPP).

 

   Emergency public works projects required to protect public health and safety are    not required to prepare a SWPPP, nor are they required to file a NOI.

 

      °  File Notice of Intent(NOI)

 

      °  File Notice Of Termination(NOT)

 

•  The Riverside County Transportation Department also builds roads on State     Highways.  These projects are regulated by the Caltrans’ Stormwater      permit.

 


 

 

Notice of Intent(NOI)

 

A Notice of Intent must be completed for projects that disturb more than 1 acre of soil.  All NOI’s will be filed by the Construction Inspection Office’s NPDES Coordinator.

 

Construction activity subject to the General Permit includes clearing, grading, and disturbances to the ground such as stockpiling, or excavation that results in soil disturbances of at least one acre of total land area, which also includes the construction staging area(s).  Construction activity does not include routine maintenance to maintain original line and grade, hydraulic capacity, or original purpose of the facility, nor does it include emergency construction activities required to protect public health and safety. Dischargers should confirm with the Transportation NPDES Coordinator whether or not a particular routine maintenance activity is subject to the General Permit.

 

NOI and SWPPP must be in place prior to starting construction.  DO NOT send SWPPPs to the Regional Boards or the State.

 

Notify the Transportation NPDES Coordinator when a project will be constructed in more than one Region before sending a NOI.

 

Project Changes:  Revised NOIs and SWPPPs are required for changes.  An unforeseen increase of total area of construction would require an updated NOI and SWPPP.

 

A copy of all NOIs must be sent to the Transportation NPDES Coordinator.  Send NOIs by certificate of mailing and ensure documentation of mailing is in project file.

 

 

FEES

 

Santa Ana Region:


   No Fee payment required. Mail NOI to:          
   Santa Ana Regional Water Quality Control Board
   Inland Stormwater Unit
   3737 Main Street Suite 500
   Riverside, CA  92501

 

San Diego(Santa Margarita) Region:


   Send fee payment and mail NOI to:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water Section
   PO Box 1977
   Sacramento, CA  95812-1977
    -or-
   Overnight Mailing Address:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water, 15th Floor
   1001 I Street
   Sacramento, CA  95814

 

Whitewater Region within MS4 Boundary:


   No Fee payment required. Mail NOI to:
   Colorado River Basin Regional Water Quality Control Board:
   73-720 Fred Warring Drive, Suite 100
   Palm Desert, CA  92260

 

Whitewater Region outside of the MS4 Boundary:


   Send fee payment and mail NOI to:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water Section
   PO Box 1977
   Sacramento, CA  95812-1977
   -or-
   Overnight Mailing Address:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water, 15th Floor
   1001 I Street
   Sacramento, CA  95814

 

Please use the following task codes for fee payment coding:

   Task Z1600 - SMR Santa Margarita Permit Fees for Construction     
  

   Task Z1620 - SAR Santa Ana Permit Fees for Construction               
   

   Task Z1675 - Whitewater Permit fees for Construction    


 

 

Notice of Termination (NOT)

 

A Notice of Termination must be sent as soon as the project construction endsAll NOT’s will be filed by the Construction Inspection Office’s NPDES Coordinator.  Send NOT by certificate of mailing and ensure documentation of mailing is in project file.  Copies of NOTs must be sent to the Transportation NPDES Coordinator.

 

Santa Ana Region:


   Mail NOT to:  
   Santa Ana Regional Water Quality Control Board
   Inland Stormwater Unit
   3737 Main Street Suite 500
   Riverside, CA  92501

 

San Diego(Santa Margarita) Region:


   Mail NOT to:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water Section
   PO Box 1977
   Sacramento, CA  95812-1977
   -or-
   Overnight Mailing Address:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water, 15th Floor
   1001 I Street
   Sacramento, CA  95814

 

Whitewater Region within MS4 Boundary:


   Mail NOT to:
   Colorado River Basin Regional Water Quality Control Board:
   73-720 Fred Warring Drive, Suite 100
   Palm Desert, CA  92260

 

Whitewater Region outside of the MS4 Boundary:


   Mail NOT to:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water Section
   PO Box 1977
   Sacramento, CA  95812-1977
   -or-
   Overnight Mailing Address:
   State Water Resources Control Board
   Division of Water Quality
   Attn:  Storm Water, 15th Floor
   1001 I Street
   Sacramento, CA  95814